Calculating Machine Run Time

During normal operation, operators load welding machines with frame components to be welded. The loaded parts enter a robot welding cell and a completed frame exits. Operators unload the completed frame and load more components in preparation for the next welding cycle.

If production goals are not being met, it's important to know if machine downtime or operator inefficiencies are the problem. To determine where the source, facilities need to accurately measure and report machine run time back to a control location.

Description

PLC logic added to the welding machine can turn on an output when the allocated process time is exceeded. This output is wired to an input of a DX80 Node. The Node’s input is transmitted back to a DX80 Gateway connected to an HMI that logs overage time. Accumulated overage time is totaled for each shift and operator.

Accurate work time is gathered at the welding machine and wirelessly transmitted back to a central control location for logging without running new data wires.

Based on real-time data collection, facility managers are able to accurately verify when the delays are the result of machine down time and when the delays are the result of operator inefficiency.

SureCross DX80 Gateways

A master communication device used to control and initiate commands to other devices in a wireless network.

Learn more »

SureCross DX80 Nodes (10-30V dc)

A Node provides sensing capability in a remote area and communicates data back to a Gateway.

Learn more »

Sign up for eNews

Industry solutions, application tips, new products, quick video tutorials, trends.

Subscribe Now »

Food & Beverage

Is your line competitive? Innovative, high-quality solutions for every phase of production. Enjoy increased accuracy, greater productivity, cost savings.

Learn more »

Worldwide Distributors

Banner has more than 2,000 distributors worldwide - ready to help you. Enter a U.S. zip code


Find international distributors